Concordia University, Nebraska

Construction updates and photos

Construction updates

June 2008

The push is on to enclose the of the arena section of the Health, Human Performance and Athletic Center before. Construction has continued despite heavy spring rains. Read the progress report from Mike Koch of the Kiewit Building Group below:

June status update from Kiewit Building Group:

 
Footings and foundations are 95% complete, 
with a break in the weather these could be 
complete in a week or two.

Structural steel erection is moving forward, 
with the backfill of arena complete this allowed 
the upper level footings to be placed which 
when complete made it possible to complete 
the structural steel erection.  There still 
remains some detailing and miscellaneous 
steel to erect, but the main structure of the 
arena is now in place.  The structure for the 
field house is scheduled to begin erection 
by middle of June.  

With structural steel complete, the exterior 
skin of the building which is precast 
concrete panels have been placed on all 
foundation walls from the lower level.  

Metal stud framing as well as masonry 
are progressing in the building, the majority 
of interior walls in the arena have been 
built, as the exterior of the building is 
completed and the building is enclosed 
drywall and finishes will continue.  

Lower level concrete slabs have been on 
hold due to the continuous wet weather, 
as it starts drying out, different areas in 
the lower level will have the concrete 
floors placed.  

The overall project is moving forward, 
we are working through the rain and wet 
weather, the project schedule is to have 
the building fully enclosed by this coming 
fall to allow for the interior finishes to be 
completed through this coming winter.  
The site will be graded and have first 
course of the parking lot in place by the 
end of fall.

View of the arena from the P.E. Building parking lot; structural steel for the fieldhouse can be seen on the far left

View of the fieldhouse structural steel and the HHPAC main entrance


April 2008

Winter is finally loosening its grip on Nebraska and, for construction of the arena section of the Health, Human Performance and Athletic Center, this means a quickened pace for building progress. Read the progress report from Mike Koch of the Kiewit Building Group below:

April status update from Kiewit Building Group:

 
The lower level concrete footings and 
foundation walls are complete. With these 
activities done, Hartmann Construction is 
now able to backfill these foundation 
walls.  This work will begin on the east 
side of the building, this work precedes 
footings on the upper level that need to 
be completed. Once these footings on the 
upper level are finished, the remainder 
of the arena’s structural steel can be 
erected as well as the start of the 
fieldhouse footings.  The fieldhouse 
pre–engineered building will then be 
erected which is scheduled to arrive the 
first week in May.

Activities currently occurring in the arena 
are the final detailing of the structural 
steel, mechanical & electrical rough in, 
masonry block walls and concrete slab on 
deck as well as concrete slab on grade pours.

Activities soon to start are the exterior 
of the building’s precast concrete panels 
which are scheduled to start arriving on site 
in mid April, this as well as roofing the 
high roof over the actual basketball court.

With the weather changing and turning warmer 
the progress of the building will begin to 
move much faster than it has through the winter, 
the project teams main objective for the next 
few months is to have the building closed 
in by September to allow for the mechanical 
systems to condition the building, which in turn 
will allow for construction and finishes to be 
completed through this next fall and winter. 

Industrial strength smothing of the cement on the second floor of the HHPAC arena

 

January/February 2008

Despite weeks of cold weather, construction of the arena section of the Health, Human Performance and Athletic Center continues to move along. A milestone was reached Feb. 7 when the arena's first main joist (see image, below) was set. Read the progress report from Mike Koch of the Kiewit Building Group below:

First joist set on the HHPAC arena (courtesy photo)

January status update from Kiewit Building Group:

 
Grading: Hartmann Construction has completed 
the over excavation and recompaction of the 
building excavation. The next phase of grading 
will be backfilling the foundation walls. 
 
Concrete Footings and Foundation Walls: 
Stephens & Smith Construction is 
proceeding with the building footings and 
foundation walls. This process has been slowed 
by the cold weather and moisture, but they are 
working ahead of the structural steel. The 
lower level footings and foundation walls are 
scheduled to be complete by mid-February 2008. 
 
Structural Steel: Davis Erection is proceeding 
with structural steel erection, sequence one 
has been erected, with sequence two scheduled 
for delivery on January 14, 2008. Upon arrival 
this will be erected followed by the last sequence 
to arrive in mid February. 
 
The next scope of work to start will be the 
Mechanical and Electrical underground in the 
lower level of the building. This work will proceed 
the concrete slabs (floors). 
 
Precast concrete panels will be the next phase 
of the exterior of the building that will begin 
sometime early spring. 
 
Office: We are currently proceeding with 
submittals and samples of the finishes of the 
building. When selected these items will be 
ordered, with a project goal of having the 
building enclosed by next winter. 

 

November 2007

The arena section of the Health, Human Performance and Athletic Center is currently under construction. Read the progress report from Mike Koch of the Kiewit Building Group below:

Project update from Kiewit Building Group Inc.


Grading: Hartmann Construction is almost complete with the overexcavation and recompaction of the building pad. They have the southwest corner left as of 10/30/07. Once they have completed this we will be able to place concrete footings for the entire lower level of the building.

Concrete footings and foundation walls: Stephens & Smith Construction has completed the exterior footings on the southeast, east and north of the lower level. They are working on the east foundation wall placing a section about every other day. They will progress with exterior footings ahead of the wall construction, to include beginning the interior footings on the east half of the lower level to allow for structural steel erection to begin the last week of November.

Crane is scheduled to arrive the week of Thanksgiving, with structural steel to start the following week.

The concrete footings, foundation walls will continue through the winter as well as structural steel. Precast concrete would be the next phase which would follow structural steel erection.
Pouring the south wall:

HHPAC construction photos from Nov. 7, 2007

Created with Admarket's flickrSLiDR. Photos by Kate Nixon.
Athletics pages are updated by Concordia's SID staff. Questions, comments:
© 2008 Concordia University, Nebraska
800 N. Columbia Ave. Seward, NE 68434
800-535-5494
Login